|

|
|
Client Name: Honeywell
MDC® was asked to investigate and provide a project analysis of a $104 million fixed-price contract for the expansion of an existing Integrated Highway Monitoring and Control System managed by a Turnpike Authority. This system is a traffic management and data acquisition application supporting travel through the heart of a major east-coast city.
|
|
Read more...
|
|
|
Client Name: NJDOT
MDC® was asked to investigate and analyze a contractor’s claim for the construction of an interstate highway interchange and inspection station. Unique geological conditions were alleged by the contractor to be responsible for a doubling in the value of the completed project. MDC® conducted a detailed Forensic Project Management and geotechnical investigation of the site to determine if the alleged conditions impacted the project.
|
|
Read more...
|
|
Client Name: NEPCO
MDC® was requested to provide expert analysis to an EPC contractor in a multi-party insurance litigation concerning a project in Pakistan. MDC® performed an expedited review of both technical and scheduling issues and worked with outside counsel in the UK to identify and analyze project delays and identify their relationship to technical and contractual issues, including force majeure events, physical damage to equipment and delay causation.
|
|
Read more...
|
|
Client Name: Stone & Webster Engineering, Inc.
MDC® was asked to investigate and analyze a contract with Petroleum Development Oman (PDO) for the detailed engineering and construction of a gas-fired turbine electric generating plant located in Oman at Saih Rawl. The power plant was to supply electrical power to the national grid and to the adjacent gas processing plant. A waste heat recovery unit in the power plant was to provide process heat to an adjacent gas plant being constructed by others.
|
|
Read more...
|
|
Client Name: Hamad Medical Center
MDC® was asked to undertake a detailed analysis of the mechanical system design for this middle-eastern advanced facility. The chiller plant capacity was in question given the multi-purpose use expected for this development.
|
|
Read more...
|
|
Client Name: Schering-Plough
Singapore Pharmaceutical Project - MDC® was asked to investigate and analyze the delay and cost overrun experienced on this bulk pharmaceutical manufacturing project in Singapore. MDC® conducted extensive site visits and personnel interviews to determine the major problems experienced in the construction of the facility.
|
|
Read more...
|
|
Client Name: Durr Automation
MDC® was retained by a Prime Contractor against General Motors on a $200MM(+) expansion project. MDC® assisted the prime contractor in preparing its statement of claim as well as defending itself against claims brought by their subcontractor. MDC®’s analysis work involved verification of labor and equipment costs and attribution of costs to various conditions including the impact of design changes, local plant requested changes and the unforeseen discovery of hazardous materials and its removal which disrupted the planned work flow.
|
|
Read more...
|
|
Client Name: Sun Oil Company
MDC® was retained to review engineering, procurement and construction issues concerning the development of a coke (coal) manufacturing plant in Indiana. Our client’s damages stemmed from the differential movement of the sub-grade beneath the coke oven battery foundations and the failure of the coke ovens’ exhaust gas system to maintain adequate negative process pressures.
|
|
Read more...
|
|
Client Name: Talley Industries
MDC® was retained by an airbag manufacturing company to consult and provide expert witness services for the evaluation of a $40 million claim against our client for defective design and construction of an airbag manufacturing plant. After the plant was sold to a third party, our client constructed additions and modifications to the plant, increasing production capacity dramatically. Part of the plant in which the explosive pellets are manufactured was involved in a catastrophic failure.
|
|
Read more...
|
|
Client Name: Dean Mead
MDC® was retained by a university in Florida to develop an analysis of the events and issues that arose during the construction of the university buildings. MDC® performed a comprehensive schedule analysis of the causes and liability for delay during the project. This analysis required verification of the contractor’s initial schedule and the subsequent updates to determine their accuracy and reliability as a basis for analysis.
|
|
Read more...
|
|
Client Name: Catasauqua Area School District
MDC® was retained by a general contractor and a Pennsylvania school district, to analyze change orders submitted by the general contractor to the school district for excessive costs associated with the removal of rock found after excavation of the proposed site for a new high school. The new high school was first estimated with a total budget amount of $20,995,100 with actual construction costs exceeding $25,356,024. MDC® determined that due to poor planning and testing by the Architect the school district was entitled to recover the excessive costs for rock removal from the Architect.
|
|
Read more...
|
|
Client Name: Sambe Construction Company
Sambe Construction Company constructed a new 20,000 SF two-story building and renovated a 64,000 SF existing two-story building for the Millville Early Childhood Center. It was a competitively bid contract awarded by New Jersey State Construction Corporation (NJSCC) and was scheduled for completion on September 7, 2004.
|
|
Read more...
|
|
Client Name: The Farfield Company
MDC® was retained by The Farfield Company to conduct an analysis and estimate damages associated with an inefficiency and extended duration claim made by Farfield in the execution of a major project at Rancocas Valley High School in Mount Holly, NJ. Included in the case was an assessment of the impact of the owner’s decision to terminate the project general contractor, the timelines of said termination, the timeliness of the assignment of a replacement general contractor and the foreseen ability of the need to terminate (or appropriateness of the initial award) on the overall execution efficiency and costs incurred by Farfield to complete the project. MDC®’s analysis included efficiency/inefficiency calculations using a measured mile approach and resultant schedule and cost impacts.
|
|
Read more...
|
|
Client Name: NEPCO
MDC® provided expert analysis and support to a design-build contractor in a dispute with a major equipment vendor. The dispute centered around the vendor’s late delivery of improperly fabricated Heat Recovery Steam Generator (HRSG) components. MDC® evaluated the impacts arising from the vendor’s performance including delays to the project schedule, productivity loss to the installation subcontractor, and monetary damages to the design-build contractor.
|
|
Read more...
|
|
Client Name: RPS Consulting Engineers/Dublin City Council
The Dublin Bay Submarine Pipeline project is part of a massive $300 million effort to improve water quality in Dublin Bay. The entire project consists of the Ringsend Wastewater Treatment Works, a new pumping station, and a 10.5 km pipeline under Dublin Bay to bring the wastewater to Ringsend for treatment.
|
|
Read more...
|
|
Client Name: Travelers Insurance
Travelers sought expert assistance from MDC® analyzing circumstances leading up to the termination of Manshul Construction by Nassau County in connection with Manshul’s work on a project at the Nassau County Community College. The County also had subsequently debarred AETNA Casualty (Manshul’s surety) from underwriting other contractors in the county and claimed completion costs from AETNA and its successor surety Travelers.
|
|
Read more...
|
|
Client Name: Stone & Webster Engineering Corporation
MDC® was retained to review the overall project to determine the potential claims and to estimate costs for possible recovery from the owner, as well as to review and evaluate subcontractor claims. MDC® performed investigative and analysis work both on-site in Saudi Arabia, and in MDC®’s home office.
|
|
Read more...
|
|
Date: 1/12/2011 to 1/15/2011 Location: Walt Disney World Swan Hotel - Orlando, FL View event details
|
|
Read more...
|
|
|
|
|
|